In an incredible schedule of 14 mat pours in 9 weeks that were all turn key projects for Conco, one week especially stood out. September 24th through October 1, 2022, brought Conco four mat pours in one week. It started with the Tasman East Apartments, then Dwight & Milvia and The Station jobs. We finished up the week at the 24th & Waverly project. These projects are all turn-key projects for Conco. In addition to concrete pumping, we are providing the rebar, place and finish work, formworks, and shotcrete.
Conco poured 13,794 yards of concrete at these four mat pours in that week alone. We averaged 450 yards poured per hour for most of the pours. Each jobsite is unique in its challenges and our teams impressed not only us, but the General Contractors, the City’s, and the other trades on the jobs with their diligence and advanced planning. We not only got the job done, but got it done as safely as possible.
Our Reinforcing services set the stage for each of these successful pours. Conco Reinforcing delivered 100 loads of rebar, totaling 4,000,000 pounds for the combined four pours for that week alone. This was all made possible with the contribution from Conco’s state of the art rebar fabrication facility in Benicia, CA. The detailers and project engineers at the office and the crew at our rebar facility tirelessly to get the rebar ready for each of these jobs.
It was a good week, and these pours were injury free thanks to the hard work of our Safety team and the Conco employee’s commitment to safety on the jobsite. Conco strives to provide its customers with not just the best option but the easiest one. We truly strive to be a one stop shop for our customers and passionately provide a service that has created strong relationships over our 60 years in the industry. With one phone call you can take care of it all.