Tacoma Convention Center Hotel
Update
The Tacoma Convention Center Hotel developed by Yareton Investment & Management will offer 300 rooms and retail spaces and the new Marriott branded hotel. Expected to open in 2020, the 4-star hotel will rise 23 stories, include 304 guest rooms, and will be connected to the Greater Tacoma Convention Center. It will also feature a 10,000 square foot grand ballroom, retail space, and other function rooms. The hotel will serve as the anchor hotel for the convention center, which has struggled recently to land larger convention and trade shows because of the lack of nearby hotel rooms.
The Conco Companies NW Division is working a 7-day cycle in the tower, pouring the vertical the same day as the slab is poured with a self-climbing core form system (supplied by FCI). The tower portion, consisting of the hotel, continues to L23 + a cantilevered concrete roof. The project will utilize 5,550,000 lbs. of Rebar, 25,000 cubic yards of concrete, and 430,000 linear feet of post tension cables. Conco is scheduled to pour-out the project by June 2019.
The Conco Companies will begin work on the new Tacoma Convention Center Hotel in August 2017 and we expect our part of the project to be completed in early 2019. The $20 million mixed-use development which adjoins the Greater Tacoma Trade and Convention Center and will include condominium and retail space in addition to a 300-room Marriott Hotel. Ankrom Moisan Architects designed the new building to enhance the conference amenities currently available in the city, which will include a 10,000 sq. ft. grand ballroom and 9,000 sq. ft. of other function rooms within the hotel.
Conco’s extensive services include concrete pumping, reinforcement, formwork, shotcrete, and finishing. As the project will be the largest one in the city, Conco was selected for the job due to our extensive portfolio of big projects as well as our ability to handle an aggressive schedule. In fact, one of our first projects in the Northwest was the Tacoma Marriott Hotel in 2004, which is located across the street from the new job site. Scheduled to open in the summer of 2019, the high-rise will be the second tallest building in the city.
Related blog posts:
https://www.conconow.com/tacoma-convention-center-hotel/
https://www.conconow.com/tacoma-convention-center-hotel-project/
Details
Location: Tacoma, WA
Project Size: 433,000SF of elevated deck / 17 floors
Yareton Investment & Management LLC
General Contractor:
Absher Construction Company
Architect:
WRNS Studio